DOCUMENT 09 · ILLUSTRATIVE SERIES A PLANNING MODEL · USD MILLIONS · AUGUST 2026

Three-Year Milestone Budget

The $15 million use-of-funds model, annual plan, milestone gates, and quarterly cash requirement.

Year 1

$4.00M · 27%

Alpha architecture, prototype, and bench evidence. Ending cash $11.00M.

Year 2

$5.95M · 40%

Beta units, verification readiness, and regulatory alignment. Ending cash $5.05M.

Year 3

$5.05M · 34%

Pilot-ready technical, evidence, and operating package. Ending cash $0.00M.

Use of funds

CategoryAllocationYear 1Year 2Year 3Total
Engineering + prototype35%$2.40$2.10$0.75$5.25
Testing + regulatory20%$0.25$1.50$1.25$3.00
Clinical + research evidence15%$0.15$0.75$1.35$2.25
Software + data platform12%$0.65$0.70$0.45$1.80
Team + operations10%$0.45$0.55$0.50$1.50
Contingency + working capital8%$0.10$0.35$0.75$1.20
Total100%$4.00$5.95$5.05$15.00

Milestone-based capital release

GateTimingCumulativeIncrementRequired deliverablesDecision test
1Month 3$0.75M$0.75MRequirements, initial risk register, architecture optionsFeasibility confirmed; scope refined
2Month 7$2.00M$1.25MModeling results, architecture review, updated quotationOutput concept and safety architecture credible
3Month 12$4.00M$2.00MAlpha prototype, bench data, calibration methodAlpha meets agreed acceptance criteria
4Month 18$7.00M$3.00MBeta design, beta units, software baseline, test readinessReady to enter formal verification
5Month 24$10.50M$3.50MVerification, pre-compliance, human factors, regulatory updateEvidence supports pilot preparation
6Month 27$13.50M$3.00MSupplier/service plans, research readiness, pilot sitesCommercial and operational readiness supported
FinalMonth 30$15.00M$1.50MFinal reports, BOM, cost model, pilot recommendationBoard approves pilot or stops/re-scopes

Quarterly cash requirement

Y1Q1Y1Q2Y1Q3Y1Q4Y2Q1Y2Q2Y2Q3Y2Q4Y3Q1Y3Q2Y3Q3Y3Q4
Spend0.750.951.101.201.401.451.501.601.501.351.201.00
Cumulative0.751.702.804.005.406.858.359.9511.4512.8014.0015.00

Planning principle

Capital is released only after written acceptance of deliverables, updated technical risks, actual-to-budget review, revised cost-to-complete, IP documentation, and board authorization.

Important limitation: this is a management planning model — not an engineering vendor quote, audited forecast, or commitment to spend. Amounts and timing must be revised after competitive quotations, regulatory classification, study design, supplier diligence, and board review.